14 October 2011 13:29 by H+H UK Limited
Ribbon Court Care Home, Coventry
Architect: Michael Ramus Architects Ltd
Contractor: Mansell Construction Services Ltd
Location: Foleshill, Coventry
Property description:
The four-storey development comprises
50 one and two-bedroom apartments for
residents with special care needs, where
the on-site amenities include consultancy
rooms, activity rooms, communal
lounges, a hairdressers, café restaurant,
landscaped garden and a waterfall in the
reception area.
“Ribbon Court is one of the first
schemes in the country specifically
designed to meet the new and
emerging needs of older people from
the area’s diverse communities.”
Jean Tompkins
Head of Health & Social Care
Ashram Housing Association
Executive summary:
H+H supplied a through-the-wall solution
to streamline the schedule of work,
within a design to achieve a very good
BREEAM rating. A single supply solution
was provided for this Modern Method of
Construction (MMC), with all the aircrete,
ties, mortar, damp-proof course (DPC),
cavity trays and bed-joint reinforcement
being ordered together and delivered
on one lorry, streamlining both the
pre-construction procurement and the
construction on site.
“We usually fill a skip every day
for this scale of development, but
constructing with Multi Plate and
Thin Joint meant that the waste filled
only two skips per week, instead of
every day. This must be better for the
environment and reduces costs.”
Joe Sutton,
Site manager, Mansell
Product used/aircrete specification: 24,000
Multi Plates (8,000m2) with the Thin-Joint
bonding system.
Internal separating walls –
Constructed to provide good levels of
sound insulation, using a 100mm cavity
between the two leaves of 100mmthick
Multi Plates, parge-rendered and
then 12.5mm plasterboards on dabs
each side. This construction passed 30
airborne sound tests, with results ranging
from 48dB to 60dB. The majority of the
results were around 50dB to 55dB.
External cavity walls –
These were constructed using 100mmthick
Multi Plate inner leaf with
brickwork outer and 100mm insulation
injected into the cavity. This achieved
a U-value of 0.29W/m2k. The inner leaf
was finished using 12.5mm plasterboard
on dabs with a skim plaster.
Aircrete compressive strength
Ground level 8.7N/mm2
1st floor 7.3N/mm2
2nd floor 7.3N/mm2
3rd floor 3.6N/mm2
“In comparison to timber-frame and
SIPS, there is less movement with
aircrete, less shrinkage and it is much
easier to make future adaptations and
alterations.”
Simon Lipinskis
Design and build co-ordinator, Mansell
Reason for specifying Thin-Joint with
H+H aircrete:
A modern method of construction with a
fast-track streamlining capability to achieve
high thermal insulation without the fire
risks of timber-frame. Using the Thin-Joint
build method also had significant speed
advantages and, as a result, the project was
completed four weeks ahead of schedule
with associated cost advantages.
Traditionally mortared concrete blocks with
timber-frame was the other option. Without
timber however, there was no risk of arson
attack during site closures at nights and
weekends. Traditional concrete blocks
would have been 60% slower to lay than
Multi Plates with Thin Joint.
The larger-format Multi Plates
(610x375x100mm) meant that three
courses were eliminated per lift. Along
with the thinner 2mm joints using 80%
less volume than conventional mortar, this
made for a much quicker, cleaner and
more airtight building. The external walls’
U-value was 0.29W/m2k.
With H+H’s early stage involvement with
the design team, the floor heights were
designed to match the full Multi Plate
unit, which meant no lengthy and wasteful
cutting at these points. Together with
the thinner bonding joints and larger
dimensions of the Multi Plates, this
reduced waste levels to approximately one
fifth of what they would have been.
“We were knocking weeks off Mansell’s
original programme, because the
Multi Plates are so straightforward and
simple to use with Thin Joint. And this
was our first use. The system’s sheer
speed advantage is matched by its
straightforward cleanliness, not creating
any droppings into the wall cavities – so
there is minimal wastage too.”
Stuart Kennedy
Managing director, SK Brickwork
Advantages:
This development’s compact site provided
little space for the silos required by
conventional mortar. H+H’s Thin-Joint
requires no silos or mixing plant, because
the Celfix mortar comes pre-mixed in
20kg bags requiring only water, a bucket
and a whisk. This means everything could
be stored within the building’s U-shaped
footprint.
Each 610mm x 375mm x 100mm Multi
Plate weighs 20kg or less, which means
they’re safe for contractors to handle
manually, according to HSE guidelines and
contributed greatly towards Mansell’s “Zero
Harm” philosophy.
H+H Multi Plates are manufactured to
extremely tight dimensional tolerances and
are supplied specifically for use with H+H’s
Thin Joint mortar. Their accuracy ensures
that little or no levelling is required, as
Multi Plates are laid, resulting in a quick
and high quality build.
Multi Plates are very environmentally
friendly, manufactured by H+H using up
to 80% recycled material (pulverised fuel
ash), waste recovered from coal-fired power
stations that would otherwise be destined
for landfill. They can be used as a part of
construction solutions which achieve A+ in
the BRE Green Guide.
“H+H’s whole-wall solution helped to streamline both the specification and the
construction itself on site, by including all the aircrete, ties, mortar, damp-proof course,
cavity trays and bed-joint reinforcement. This meant only one lorry delivery instead of
requiring the management of many loads.”
Joe Sutton Site manager, Mansell
Submit your news
Send us your construction related news and press releases to feature on specifinder.com free-of-charge. Email them to [email protected]
Add your company
An entry on specifinder.com gives you exposure to over 32,000 unique visitors a month. For further information, please email [email protected]
Tweets by @specifinder


